SamTrans Logo art
 

Marsh Road to Woodside


This project is for the preparation of the project study report (PSR), project report (PR) and the environmental documents for the following work: (A) extending route 84 north on a new alignment from Marsh Road to Woodside Road/Seaport Boulevard, (B) widening Woodside Road from Broadway to El Camino Real and (C) reconstructing Route 84/Woodside Rd. I.C.  The purpose of the project is to alleviate existing and projected traffic congestion, provide a parallel reliever route for Route 101 between Marsh Rd. and Woodside Rd. and improve traffic operations at the intersection with Marsh Rd./Rte. 84 and with Woodside Rd./Seaport Blvd.  The project scope is anticipated to include detailed design and construction at a later date as the Board authorizes future budget.

 

Progress:

Project A: PSR approved. Project on hold.

Project B: PS&E nearing 95% submittal

Project C: PSR approved.  Contract for PR/ED to start 2/02 

PR/ED for 84/101 interchange will not include the Rte. 84 Extension project, but will not preclude adding the extension to the system in the future.

The Board will need to authorize additional funding for future project activities.



 

Quick Hits

Progress Reports

Expenditure Plan
2009-2033


Dumbarton Rail

Highway 101 Auxiliary Lane Project:
Millbrae Avenue to Third Lane


Application for CAC Member
(PDF, 28 KB) - (MS WORD, 110 KB)

Procurement

Jobs