Home

Site Map

Contact
|
|
Oyster
Point Blvd. Phase II |
|
|
This project is for the highway improvements at the Oyster
Point Interchange on Route 101. These improvements are being done in order
to provide relief to freeway traffic congestion in the vicinity. This
project will be done simultaneously with Phase I (the construction of the grade
separation and easier freeway access), Phase II (Flyover Facility) and Phase III
(Hook Ramps - Project No. 719) to minimize the costs and conflicts in the design
and construction of these improvements.
Evaluation of the construction cost reduction incentive
program has been completed.
Future activities include completing the foundation work
for the bridge piers and bridge abutments and begin bridge framing.
|
|
|

|