Oyster Point Blvd. Phase III


Phase III-A

This project is for the hookramps of the Oyster Point Interchange project on Route 101.  This was approved by the TA Board by authorization No. 1999-31.  The hookramps will provide a southbound off-on connection to Route 101 from Bayshore Blvd. which connects Brisbane and South San Francisco.  The funding breakdown is as follows:

a) PG&E:   $5,040,000
b) Telecom:   $1,240,000
c) SF Water Dept.:   $3,100,000 
d) Measure A: $10,750,000
e) Loan to SSF (Job #720): $10,750,000
Total: $30,880,000

The City of South San Francisco will obtain a loan from Measure A funds (item e) that is to be repaid with revenues from the development fees.

The project is broken into 2 contracts.  Contract 1 is utilities & rough grading.  Contract 2 is the roadway work.

Contract 1 (utilities & rough grading) - began fill replacement, storm drainage and water line fabrication.  Contract 2 - began the 95% design.

Future Activities: Contract 1 - Continue construction of the joint trench and fill replacement, begin installation of 16", 48" & 60" Water lines and complete retaining wall No. 4

Phase III-B

This project is for the funding of a loan, of Measure A funds, to South San Francisco in connection with the Oyster Point Interchange Project phase III - A.  Project #719.

The City and the SMCTA have entered into a loan agreement.

This money will be repaid to the SMCTA by the City of South San Francisco so that the total project costs will have a net of $0.  The loan repayment will be required by 2008.

Future activities include repayment of the loan by 2008.



 

Quick Hits

Progress Reports

Expenditure Plan
2009-2033


Dumbarton Rail

Highway 101 Auxiliary Lane Project:
Millbrae Avenue to Third Lane


Application for CAC Member
(PDF, 28 KB) - (MS WORD, 110 KB)

Procurement

Jobs