This project is for station improvements and consolidation
studies of the Burlingame, Hillsdale, Bay Meadows and Atherton stations.
It will include the production of orthographic photo and planimetrics of the
entire Caltrain ROW and the Dumbarton corridor. Also a GIS system will be
developed, which will be used for project development as well as
engineering. This mapping will be used by the JPB, SamTrans and the TA
agencies. This project is tied to Jobs # 2006 and 9920.
The orthographic photo and planimetrics from San Francisco
to San Jose have been completed. UPRR's PMV has completed the data
collection.
Attempts to collect VTA's share of reimbursement for the
project have failed.
Future activities include completing the monumentation
work from San Francisco to San Jose, completing ROW parcels information and
completing system training and manuals.
|